Blog

RVA supports Maltese energy giant

Enemalta Corporation – the state-owned energy utility giant responsible for generating and providing electricity to the Maltese islands – has begun planning for the future.

Specialist UK-based engineering consultancy RVA Group is currently supporting Enemalta in its review and assessment of two existing power stations – Marsa (MPS) and Delimara (DPS) – as part of the company’s strategy to update their electricity generation technology.

Beginning with the preparation of outline plant decommissioning, this initial phase of work comprises of a monitoring programme and a waste management plan is to be devised as a result.

As MPS is expected to be phased out by 2015, the RVA team must go a step further and develop a full decommissioning plan for this plant with recommendations as to the most suitable de-planting options, associated dismantling and demolition techniques and finally the civil works required to reinstate the site ready for subsequent use. A detailed safety management programme will underpin the entire strategy document.

RVA managing director explains: “As with any decommissioning project there are numerous factors to consider, which is why it is important to undertake extensive investigative work before a recommended plant decommissioning plan is prepared. There can never be a ‘one size fits all’ approach. On this particular project we have to think about the removal and dismantling in the most cost-effective way of all mechanical and electrical equipment and the structures themselves.

“This client is keen to ensure best practice from day one, therefore it is crucial that every risk is assessed and every opportunity explored.”

RVA’s plans – which are to be submitted to the Malta Environment and Planning Authority (MEPA) for approval – will detail how, in what sequence and over what period of time this project should be pursued, together with an estimate of the resources required, security protocols and the costs involved. The authorised, plans will form the basis for decommissioning implementation at the appropriate time.

Martin Attard-Montalto, division manager at Enemalta, commented: “We know we are going to need additional generation capacity in the coming years, but we have recognised the need to replace some of our outdated technology with more efficient plant. This will not only ensure legislative compliance but will significantly reduce primary fuel consumption and subsequent emissions.

“We appointed RVA following a rigorous tendering process, on the basis of their specialist expertise and proven independent experience within the field of planning for power station decommissioning. It is important that Enemalta makes not only the safest, but also the most environmentally and commercially sound decisions going forward, so this guidance and much-needed insight will allow us to progress in this manner.”

RVA has undertaken similar projects in the past – for example asset and liability assessments and baseline decommissioning plans have been carried out previously for both Magnox and British Energy, and the RVA team has recently completed detailed front end engineering support to EDP, for their power plant demolition project in Barreiro, Portugal.

Enemalta’s current power generation technology is expected to be replaced by a new plant at Delimara and by submarine interconnection to the European grid.

Notes:

Marsa power station is an electricity generating plant comprising six fired boilers, six generating turbines (30MW to 60MW), one open-cycle gas turbine, seven fuel storage facilities and four stacks (up to a maximum 75m in height). Almost all electricity produced at Marsa is derived from the combustion of HFO (residual heavy fuel oil).

Delimara power station comprises two fired boilers with two 60MW condensing steam turbines utilising HFO. Elsewhere two 37.5MW open-cycle gas turbines, two 38.5MW gas turbines and one 38MW fully condensing steam turbine (in a combined-cycle arrangement with two heat recovery steam generators) utilise GDO (gas/diesel oil) . There are also four stacks – the tallest of which is 154m in height.

A new plant at Delimara is due for commissioning mid 2012 and will consist of eight diesel engines (with selective catalytic reduction and waste heat recovery boilers), a single condensing steam turbine and four steel stacks.

Share

RVA’s expertise highlighted in industry magazine

The specialist expertise of RVA Group has been highlighted in leading industry publication Process Engineering. In the March – April 2011 issue, RVA considers the evermore challenging arena of process plant decommissioning…

“The difficult economic conditions of recent times have affected widespread processing sectors with quite overwhelming results. Unprecedented pressures have been placed on chemical, petrochemical, pharmaceutical and manufacturing companies across the globe, and very few have proven recession-resistant.

This is not to suggest there will be a permanent exodus of the processing industry, even in the UK alone. However it cannot be ignored that the number of production facilities being mothballed, rationalised or permanently closed down remains staggering. The specialist area of decommissioning may therefore be a great step into the unknown for most organisations, yet it is perhaps equally an inevitability for many.

The challenge is how to deal with the decommissioning – and in many cases decontamination, dismantling and demolition – of facilities safely, whilst at the same time cost-efficiently and with minimal environmental impact.

It should not be expected that the majority of businesses are competent to proceed with such projects without specialist external guidance. Decommissioning is not always a straightforward process and cannot be viewed merely as an extension of normal operations or the reverse of commissioning and construction. Nor should it be rushed in an attempt to achieve an accelerated exit. Decommissioning is an inherently hazardous activity and should be managed by appropriately experienced professionals, and the most important way to ensure a project’s success is getting the team right from the start. A specific set of skills and competencies is required to ensure the management of safety is proficiently catered for, and that the achievement of safety excellence is at the top of the ‘to do’ list.

The careful use of an organisation’s own engineering and production staff is in most cases a positive and value-adding move. Effective decommissioning is underpinned by a thorough preparatory and planning process whereby assets, procedures, decontamination and isolation details are comprehensively documented on an ongoing basis so that everything can be accounted for, and the plant can be brought to the required ‘known state’. No one will know this plant-specific information better than the people that have been running it, so key personnel should be involved from the outset.

However projects of this nature and scale tend to lie beyond most companies’ usual remit, and there will be areas of expertise that cannot possibly be fulfilled in-house – it is not reasonable to expect a skilled production manager for example, to become a qualified decommissioning engineer overnight. Instead the knowledge-based management support of external engineering consultants should be sought, so that any given project and its inherent risk, is competently managed.

By law, all UK demolition projects must be carried out in accordance with Construction Design Management (CDM) regulations. Revised in 2007, the regulations are not just a matter of paperwork compliance. Instead they govern the planning, coordination and management of projects to secure the health, safety and welfare of all involved. A competent and relevantly experienced CDM coordinator must therefore be appointed to oversee the project in this respect, and ensure consistency of standards.

Outside of the UK, whilst the legislative terms and job titles may differ, the principles, roles and responsibilities remain the same – manage safety to the highest achievable standards.

Beyond this there is no such thing as a ‘one size fits all’ approach. Every project has to be assessed on its own merits to ensure that a suitably skilled project team – comprising demolition, explosives, chemical, structural and mechanical engineering experts for example – is assembled for the job.

Because the decommissioning process is frequently brought about due to site closure or corporate rationalisation, it is commonly viewed as an unwelcome event and as a consequence, minimal resources are often allocated to what is an incredibly complex and high-risk activity. This can result in poor environmental, health and safety (EHS) performance, and ultimately commercial failure.

Even with the best intentions at heart, when money is tight some companies will take shortcuts, but the global downturn doesn’t mean that hazards are any less onerous, or that legislation can be flaunted. Safety should always be the number one priority.

Safety plans should be compiled in conjunction with other contractual documentation to ensure a cohesive output that does not conflict with risk management and the goal to achieve EHS excellence. Independent and specialist auditing of sites and methodology further helps to ensure best practice, but operations should be reviewed and revised as site works progress because ‘change of state’ can be rapid.

Organisations will understandably be focused on closing down their factories and plants in the swiftest and most cost-effective manner possible, due to the financial pressures that will no doubt have led to the said situation. However in truth a large majority of clients will not know where to turn next.

A feasibility and option study should provide a clear view as to the true liability, or indeed opportunity, of a decommissioning project. The findings and specialist recommendations given by independent experts with an experienced ‘demolition mindset’, could then provide companies with sufficient data and indeed confidence to pursue an innovative route that they perhaps previously deemed impossible, or may even have been wholly unaware of.

Sometimes dismantling elements of a plant for scrap whilst mothballing remaining structures is the preferable route, whereas in other scenarios complete site clearance proves the safest and optimum financial solution. Not only can direct liabilities such as hazardous material containment, security and maintenance costs, and local authority building rates be removed, but in some instances it is even possible to generate sufficient funds from scrap materials to completely cover the cost of the project.

Clearly not all decommissioning work will be self funding or cash generative, but cost-effective solutions can be devised that will help to mitigate a financially difficult situation. The recession has caused many companies to postpone important dismantling and decommissioning projects, as they simply deem them unaffordable, however they will have be tackled at a later date and in most cases at an increased cost.

The goal should always be to maximise return on assets where possible and indeed safe to do so. However factors such as plant age, former process, recovery cost, testing, market forces and commercial competition will all form part of the decision as to what should and should not be salvaged. In some instances it is efficient to recover individual items of plant for resale, however in other circumstances the dismantling of entire processes for reinstallation elsewhere, is possible.

Most importantly, organisations need an early project cost magnitude indication. This information can then be used to compile sanction grade estimates, funding applications and even determine the programme and extent of a project. Once again, specialist expertise and commercial understanding is invaluable in this respect, as factors such as plant resale value, scrap and credit recovery, market conditions and the possible effect of legislative changes, need to be incorporated alongside the direct project costs. However it is crucial that confidentiality, supply chain independence and trust are assured from the outset, so as to protect the commercial security of those involved.

Overall, making use of external expertise should be seen as a value-adding and team strengthening exercise, rather than a loss of control. Furthermore the sooner a specialist consultancy can get involved, the greater the benefit derived. Because it is the duty of the project management and engineering experts to provide safe, environmentally sound, commercially secure and cost-effective outcomes to project, companies can continue to do what they do best – run their business.

Because increasingly larger and more sophisticated world-scale installations are reaching the end of their life – and because legislation and environmental pressures are becoming evermore stringent – it could be argued that decommissioning is becoming an evermore complex practice.

Yet ever-advancing technology and improved knowledge does mean that project solutions are increasingly innovative, cost-effective and safe. The use of explosives for example is now much more precise, and specifically designed equipment is now commonly used to access hazardous areas where previously operatives may have been unavoidably placed at risk.

With an almost bizarre twist, preparing plant and machinery for dismantling and demolition can be less onerous than actually operating it throughout its life cycle, so long as the company has adequately planned for the situation and the best team is assembled for the job.”

To view the full article in print, visit http://digital.centaur.co.uk/processengineering/pe_032011/

 

Share

Maximisation of income for INEOS

Seeking the advice of a specialist engineering consultancy can reveal previously unconsidered opportunities and considerable cost benefits, as INEOS ChlorVinyls has found after appointing RVA Group to manage large-scale UK decommissioning projects in Barry and Runcorn.

INEOS ChlorVinyls – Europe’s largest polyvinyl chloride (PVC) manufacturer – engaged sector-specific CDM coordinators and project managers RVA Group, to oversee the safe execution of these two major projects and ensure the maximisation of income from the resale of redundant plant and metallic arisings including high-value exotic alloys.

RVA commenced its role at INEOS ChlorVinyls’ Barry site after manufacturing ceased in March 2010 as part of a consolidation of activities. Having planned to decommission and clean the site before handing it back to the landlord with the plant intact, INEOS sought RVA’s isolation and decommissioning guidance. However acknowledging the financial implications of INEOS’ proposed site exit strategy, RVA conducted a series of in-depth feasibility and option studies to investigate more commercially attractive routes for the client.

Utilising its vast knowledge and experience of asset recovery, RVA recommended that INEOS hand the site back as flat slab, as plant demolition and dismantling could generate an income from the sale of the process equipment – some had potential for reuse whereas other items (as a result of their high-value metallurgy) would create a positive income stream.

To demonstrate their confidence in the proposed alternative site exit strategy, RVA agreed to work for six weeks – at risk – to test the feasibility of their solution. If the project plan had proven unachievable, RVA would have waived all costs for work undertaken during this investigatory period.

However, as RVA had anticipated, the team was able to demonstrate that the project could be delivered with significant cost savings thus reducing the financial burden for INEOS.

Now RVA is project managing the dismantling and demolition of INEOS ChlorVinyls’ production facilities including process vessels, aluminium and concrete storage silos, a boilerhouse and three steel 1,500 cubic metre storage spheres. With a 27-man team on site, and kit ranging from excavators with shears and grab buckets to an ultra long reach machine safety remains the number one priority.

Colin Hopwood, INEOS ChlorVinyls’ site services manager for Runcorn explains the reason for RVA’s extensive involvement in the Barry site project: “RVA’s role with INEOS in fact commenced with the team’s development of a detailed redundant asset management review for our Runcorn site.

“The Company drew upon its technical engineering experience to assess a number of plants, projected costs of removal, optimised sequencing and a potential rolling decommissioning programme for several areas of the 125-hectare top-tier COMAH site. The quality and integrity of this guidance not only led to us proceeding with the Runcorn works, but I also then recommended their services to a colleague heading up the Barry project.”

Since the sequential decommissioning and demolition of five redundant chemical processing plants began on the high-hazard Runcorn site in August 2010, the site has remained operational elsewhere. Meticulous planning and project coordination has therefore been essential to ensure minimal disruption and utmost safety for all parties.

Priority was given to the complex dismantling of INEOS’ four distillation columns, ranging from 40 to 60 metres in height, which had to be dismantled to a low height before the arrival of the year’s high winds. However due to their proximity to high-hazard pipelines, and given the inherently dangerous nature of hot-cutting techniques, an alternative dismantling process had to be devised. Instead RVA oversaw the more time-intensive, but far safer alternative, of using high pressure abrasive water jets that ran around the circumference of the columns’ cut lines to eliminate the flammable risks, before the top sections could be removed with a lifting nail attached to a 500t crane.

With six months of the programme still to complete, RVA is currently planning for the dismantling of INEOS’ anhydrous caustic soda plant – a procedure that will take place in May 2011. Although the asset is no longer needed by INEOS, the plant is in good condition and is being carefully dismantled for re-erection elsewhere.

Colin Hopwood continues: “Due for completion in August 2011, the clearance of the redundant assets within our Per-Tri, Per-Tri Shipping, ACS, VDC4 and KOH plants will prepare the site for potential new INEOS ventures.

RVA’s experience supported by impressive client references and commitment to offering independent, value-adding support, cemented our decision to choose their team.”

RVA managing director Richard Vann concludes: “The scenario that we’ve seen at the two INEOS sites is one that is becoming increasingly common. Companies around the world are under great pressure to ensure that their sites are decommissioned safely, but at the same time cost-effectively. This financially challenging and inherently hazardous situation usually represents a step into the unknown for most site owners and operators, which is why specialist engineering expertise and experience is required. Our goal is always to maximise our clients’ return on assets where possible and safe to do so.”

Share

Global demand for RVA’s expertise soars

RVA Group – the UK’s leading expert in large-scale decommissioning, decontamination, dismantling and demolition project management – is preparing for a period of controlled growth in 2011 following a record-breaking 12 months’ performance.

The company, which has enjoyed year-on-year expansion since its formation in 1992, saw turnover increase by 15% from 2009 to 2010. Much of the new work is being driven by RVA’s growing international presence, with organisations from around the world turning to the Ipswich-based company for help when decommissioning major industrial processing sites.

RVA’s managing director Richard Vann explains: “Many large, complex, high-hazard installations worldwide are now reaching their end of life. This challenging area of work remains inherently high-risk so the need for our specialist engineering support in the UK and overseas is paramount.”

Having now completed in excess of 500 projects – including some of the largest process plant decommissioning assignments this country has ever seen and in locations as challenging as Turkmenistan – RVA has worked with many internationally renowned blue-chip organisations such as GlaxoSmithKline, BASF, Ineos, GrowHow, CIBA and ConocoPhillips to name a few.

In 2010 RVA’s expertise was called upon to provide project management assistance and technical guidance for a 7-hectare Portuguese power plant decommissioning project. In January the team was appointed to provide specialist demolition and safety expertise to support the clearance of a cement works in Cyprus, and now – as its overseas reputation continues to grow – RVA is receiving further enquiries from countries across Europe, including the Netherlands, France and Germany.

The website has been a key driving force in attracting global interest in recent months. With a multi-lingual homepage that can be translated into seven different languages, the site is designed to be an informative resource from which prospective clients can make informed, considered decisions about what steps to take when facing site rationalisation or closure.

Whilst RVA is looking forward to taking on new international projects, the expansion will be steady and controlled in order to maintain the company’s exemplary EHS (environment, health and safety) record. RVA will also remain committed to providing an independent, tailored service with bespoke recommendations for every client, taking into account each project’s unique factors and requirements.

To support the projected growth, two new specialist project managers have been recruited to join the company’s existing team of engineering experts, with further expansion of RVA’s skill-set planned for this year.

RVA has become well established as a UK market leader in the technically challenging field of decommissioning consultancy services, and we anticipate that projects within this country will remain integral to our business model going forward. However with the increased number of large-scale industrial site closures occurring across the globe, we are now ready to achieve our long-term strategy to become a market leader on the international stage too,” concludes Vann.

Share

Authoritative role for RVA at leading event

The specialist expertise of RVA Group has been sought by the Institution of Mechanical Engineers (IMechE), as part of an authoritative one day seminar focusing upon redundant plant.

Set to attract site owners and operators from throughout the country, the Wilton event will offer an in-depth look at the engineering and safety issues typically faced when managing redundant assets. A programme of presentations is planned for the 19th May 2011, with RVA delivering a session focusing upon “Dismantling Plant for Sale and Re-use” at 14:05.

Having completed in excess of 500 large-scale, complex and high hazard projects, RVA can offer much-needed expert guidance regarding what is usually a step into the unknown for many organisations.

An RVA director explained: “Companies across the globe face great uncertainty when assessing the viable options for redundant plant. However, day in day out, RVA works exclusively for clients within these financially challenging and inherently high-risk circumstances, to provide a much-needed professional insight into this very specialist area of engineering.

“We therefore have a lot to offer at a leading industry event such as this. Since 1992 our team has been dedicated to providing unbiased, uncompromised, knowledge-based management support – in the disciplines of decommissioning, decontamination, dismantling and demolition – so I would encourage anyone who is currently (or potentially) facing site rationalisation or closure, to attend.”

RVA’s presentation will investigate:

  • What feasible options exist for redundant plant?
  • How to establish the commercial viability of dismantling plant for sale and re-use before approaching the market?
  • How to ensure vendor control over the project execution and finances?
  • What methodology and subsequent management approach will ensure facilities are decommissioned, isolated, demolished and/or dismantled safely, whilst at the same time cost-effectively and with minimal environmental impact?
  • What potential challenges and risks are associated with this complex activity and how these can be identified, anticipated and overcome?

For further information about the event, contact RVA or visit the IMechE website.

Share

Cementing Overseas Relationships

Working with local consulting engineers PPA, RVA is developing the demolition and site clearance plan for the Moni cement works owned by Cyprus Cement Public Company, a member of the Galatariotis Group.

Share

EU Win In Energy Sector

One of Europe’s major energy operators Energias De Portugal (EDP), has appointed RVA to provide project management assistance and technical advice during their vast demolition and site clearance project in Portugal.

As the UK’s leading expert of large scale decommissioning, decontamination, dismantling and demolition projects, RVA is supporting EDP throughout the decommissioning and demolition of its 7 hectare power plant in Barreiro, Portugal.

RVA has already helped EDP prepare a detailed project specification and tender documentation, and will play a key role in the contractor selection programme. Following the appointment of a contractor, RVA is available to continue to work with EDP, providing specialist project management support and technical advise as required throughout the programme of works.

The project will include the demolition of several large structures comprising a 1,000m oil and steam pipeline, engine room, boiler, steam turbines, pumping station and two on-site reservoir tanks, each measuring 7,500m³.

Share

Scottish Multi For RVA

River Clyde Homes has selected RVA’s multi-disciplined team, to support them in the demolition of Octavia Court, a 17 storey residential block in Greenock.

RVA’s in-house demolition and CDM experts will work closely with River Clyde Homes to project manage the demolition programme and co-ordinate site operations.

The tower block will be brought down by the controlled use of explosives in early 2011, to allow for the continuation of a large scale regeneration programme. When the site is cleared, work will commence to build 14 new terraced and semi-detached homes that will house up to 56 people.

Share

Vast Jigsaw Completed

A highly complex programme of plant decommissioning, isolation, demolition and ground remediation has been completed at GrowHow UK Limited’s former 100-acre fertiliser production site at Severnside, under the guidance of project management consultants and CDM coordinators RVA.

See projects for more information…

Share

New Service To Address Current Market Conditions

RVA has developed a ‘care and maintenance’ service to support clients who wish to decommission a plant or site but not necessarily go immediately into a dismantling or clearance phase.

See the services section of this website.

Share